St Helena airport: blasting to begin

Rock-blasting in Rupert’s Valley is due to begin on 1 March 2012, as part of work to build a temporary jetty for landing airport construction materials.

People living in the valley have been promised they will get personal warnings of explosions. 

Airport contractor Basil Read is also setting up a laboratory and store in the cannery works, which closed at short notice earlier this month.

Other works in the Rupert’s area include:

  • A temporary road to the quarry
  • A workshop near the cannery
  • A platform for temporary fuel storage between St Mary’s Church and the power station

A statement from the St Helena Access Office says: ‘Further detailed information on the blasting operations will be announced closer to the date via both local radio stations.

‘Residents and workers in the Rupert’s area will also be contacted directly by Basil Read and Halcrow staff.

‘Basil Read has leased the building at which the Cannery used to operate in Rupert’s and will be carrying out minor modifications to the inside to accommodate a laboratory for testing concrete and soil samples and a dry storage area for equipment and material.’

About these ads

About Simon Pipe

Former print and BBC journalist, running St Helena Online news website about British territories in the South Atlantic at www.sthelenaonline.org and blogging occasionally on other sites.
This entry was posted in Airport and tagged , , , , , , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s